Market Bosworth

Layout presented by Dave Hewett & Pete Bettany

Why Market Bosworth

Dave grew up in northwest London close to the ex London & North Western Railway and Midland Railway lines into Euston and St Pancras stations. Both of us are members of The Leamington & Warwick Model Railway Society P4 group working on the Societies Clarendon layout (later to become Clarendon & Scrubbs Lane). This layout included the LNWR as one of the featured railway companies and, as a consequence, Pete already had a collection of models of this company. So a layout involving both LNWR and MR was considered to be a good potential subject. We turned to the Pre-Grouping Railway Atlas for a suitable subject. During this search we came across a small line in Leicestershire jointly owned and operated by the LNWR and MR. The Ashby & Nuneaton Joint Railway (ANJR).

Looking at the various stations on the line it soon became clear that Market Bosworth offered the most potential in terms of operating interest. It was by far the busiest station on the line apart from Nuneaton.

Goods services at Market Bosworth included local pickup, cattle, milk, animal feed and fertiliser supplies and general goods for the whole area.

Up sidings served a large goods shed, carriage landing, cattle dock and provender store.

Additional sidings on the Up side were used to marshal coal from local collieries for onward shipment south.

Sidings on the Down side, which included a bay siding, were used as layby sidings.

There was a small gas works on the opposite side of Station Road which was probably supplied coal via the Ashby & Nuneaton canal which ran close by. But one written information source (Ashby & Nuneaton Joint Railway by Peter Lee) suggests it was rail fed. Although no evidence of a private siding can be found we have chosen, for operational interest, to assume it was supplied by rail with the station down sidings used for exchange of gas works traffic.

In the early 1900’s the LNWR gained running rights over MR lines north of Moira. They quickly scheduled an express service from Buxton to London which ran down the ANJR line.

The line also saw a lot of through goods traffic some examples of which are:-
Manchester to Camden
Stockport to Camden
Manchester to Northampton
Nuneaton to Manchester
Burton on Trent to Banbury

Now certain criteria had to be met in designing the model.

  1. Modular in design to enable transportation to exhibitions.
  2. Wanting to be able to have the layout erected all the time it had to fit in Dave’s garage.
  3. Limit as much as possible the number of operators required in order to keep costs of exhibiting as low as possible whilst also providing a good level of entertainment to paying visitors.

Taking account of the above, particularly the space available, it was clear that a full prototype model was not going to be possible. It was therefore decided to produce a representation of the station and goods yard with all the features and facilities included.

The Ashby and Nuneaton Joint Railway (ANJR)

In the 1866 session of Parliament there was an unholy row between the London & North Western Railway and Midland Railways over two separate lines — the Midland’s Settle & Carlisle line in competition with the L&NWR’s West Coast Main Line, and the Ashby & Nuneaton line, where both railways put forward rival schemes. On the Ashby & Nuneaton Junction Railway, however, a compromise was reached whereby the proposed line was to be operated jointly by the two companies. The line did not actually run to Ashby-de-la-Zouch but to Woodville Junction, about 3/4 mile west of Ashby on the Midland Railway’s Leicester to Burton-on-Trent line. There was also a branch from Shackerstone to Swannington, which joined the Midland Railway at Hugglescote Junction just south of Coalville. Construction began in August 1869, and the joint line opened to goods traffic on 1 August 1873 and to passengers a month later.

Nuneaton had two stations. Abbey Street (MR) and Trent Valley (LNWR). Passenger services ran between Nuneaton and Ashby, Coalville, Loughborough, and Burton on Trent. In the early 1900’s the LNWR gained running rights over MR lines north of Moira. They quickly scheduled an express service from Buxton to London which ran down the ANJR line.

Overseal & Moira station closed in 1904, after which trains ran through to Moira and Ashby on the Midland Railway. The line declined following World War I and passenger service ceased on 12 April 1931. Goods service was withdrawn on 1 July 1971 and the track was removed in 1973.

Period in history

The period modelled had to be turn of the 20th century as Pete’s stock is based on this period. 1907-1909 was chosen.

Very little has been written about this small line. A couple of small books and magazine articles.

Although the line has long been closed the section between Shenton and Shackerstone has been reopened as the Battlefield Line, a Heritage Railway owned and operated by the Shackerstone Railway Society. This offered the possibility of site visits to some parts of the line.

Between the books, magazine articles, ordnance survey maps, The Historical Model Railway Society and help from the Shackerstone Railway Society it was possible to compile a reasonable level of detail on the line as a whole. A working timetable for the period was also obtained from the Midland Railway Society.

Layout Design

The layout consists of six boards, four scenic and a fiddle yard each end. This stage of layout construction is probably the most important part of the build. We were fortunate to have access to an extremely large perfectly flat surface table. By using this table and large square engineering blocks we were able to construct flat and square boards. Fortunately Market Bosworth station was built on flat land! The top sides and crossmembers are of 6mm birch ply. Two 9mm ply boards were sandwiched together to form the ends. They are 150mm deep but due to the plywood construction are fairly light. As usual alignment is with pattern makers dowels.

The boards are supported of simple wooden leg frames which are linked by strap sections to give the whole structure rigidity.

An LED lighting strip runs the length of the scenic section supported on aluminium frames positioned just inside each fiddle yard.

The layout is wired for DC only. The control panel has a mimic diagram of the track with section switches, uncoupler switches, point switches and signal switches. The circuit is configured for two operators. Interconnection between boards and control panel is by ‘D’ type connectors. A computer PC power supply powers the points, uncouplers, signals and lights. Two 15v AC transformers provide power for the controllers.

Trackwork

The track layout was produced using TEMPLOT which also generated the templates used to build the track. All the track is hand built using steel rail, Exactoscale chairs etc and plywood sleepers. Having access to a 36 inch wide CAD plotter enabled pointwork to be plotted in combinations. Once printed the template was stretched onto a flat board and the trackwork built remotely from the layout. When completed the template, with trackwork attached, was transferred to the baseboards and fixed in position. Examples of standard points, 3-way point, single and double slip and catch point can be seen around the layout.

Operation of points is by Tortoise slow motion motors.

Point rodding is produced using stools from Modelu and 0.4mm Sq.rod from MSE.

Track and general ground ballast was produced using Greenscene track ballast and Chinchilla dust/shot blast grit for sidings areas. Suitable colours and weathering were then applied.

Scenery

One advantage of building a layout of a real place is that the scenic elements are determined for you. For example the bridge, road and embankment at the station end are miniature copies of the real thing, this gives a very nice scenic break from the fiddle yard. Not so at the other end. The bridge that forms the scenic break here has been moved a number of miles nearer and also grown an extra arch to accommodate the headshunt. Consequently, although the trees behind the goods shed did exist the field did not rise up to meet the bridge. Just as well because if modelled as in real life we would have had even more flat land!

Embankments and the sloping field are made with a base of expanded polystyrene topped with a layer of Scuptamold. Ground cover uses static grass and various Woodland Scenics scatter materials.

Trees utilised the well known method of florists wire twisted together to form trunk and branches, then some postiche followed by scatter materials.

Flower beds used ready made shrubs from the Footpath Scenics range.

The seemingly endless yards of Midland pattern boundary fencing was produced from wood strip in a home made jig. The same was true for the station fencing but this time using plastic strips.

We are still in the process of adding ‘stuff’ to the goods yard. Although Market Bosworth had the largest goods facilities on the line it is a lot busier than it would have been in reality. We think it’s better for the viewing public to have something to look at rather than a blank space.

Buildings

Quite a few of the buildings still exist at Market Bosworth although modified over the years. Site visits allowed us to get dimensions of the station building, platforms, cattle dock, goods shed and signal box. This information combined with early photographs has allowed us to make accurate models. The weighbridge and stable are Severn Models kits and the signal box is a London Road Models kit. The bridges and all other buildings are scratch built using plasticard faced with South Eastern Finecast brick sheets. The station building and the waiting room required some special items not produced by the normal method of laminating plasticard. The sash windows were laser cut (three pieces per frame) by York Modelmaking to our design and the stone window surrounds were made by making masters in plasticard, creating rubber moulds and casting them in white metal. Tiles on the station, station masters house, waiting room and goods shed are self adhesive strips supplied by York Modelmaking. The only structure not constructed by the layout builders is the goods shed built by our good friend Richard Harper. It was painted and detailed by us to ensure it matched the appearance of the other structures. The provender building is interesting in that it is an accurate copy on three sides but one side is guesswork as we have no photos of that side. Naturally it is the side that faces the public!

Signals

The LNWR pattern signals are all made from Ratio and MSE parts with the exception of the co-acting Down Home where the post is scratch made with MSE parts added. Operation is by small servo motors powered from a Megapoints Controllers Servo controller board.

Control system

The Control Panel divides the layout into 25 sections which can be switched to either train operator. Each train operator selects his required route and signals before carrying out the move using Pentroller controllers. This provides substantial flexibility in the operation, particularly in terms of the use of both drivers at the same time, and thus provides a good level of movement to entertain visitors.

There are numerous hidden electro-magnets used to operate the Alex Jackson coupling system. Most of these can be switched to either driver and operated using foot switches.

There is a “back road” out of sight of visitors which is used to pass stock e.g. empty/full coal wagons, between the two fiddle yards. Operation of the “back road” is carried out by one of the fiddle yard operators using a Gaugemaster handheld controller.

Rolling stock

All the LNWR locos are London Road Models kits. Midland locos are London Road Models, Craftsman Models and Alan Gibson Workshop kits. The Black Hawthorn is a High Level kit. We use Mashima motors, High Level motors and Portescap Motor/gearbox units. Suspension systems can be springy beam, simple compensation, twin beam compensation or even part sprung and part compensated.

LNWR coaching stock is a mixture of London Road Models and Ratio. The Ratio corridor coaches are fitted with modified London Road Models corridor connections which articulate so there is no gap. They are held together with miniature magnets.

Midland coaching stock is Connoisseur and Mercian Models kits.

The LNWR Railmotor is an ex Mallard Models kit from Blacksmith Models

Wagon stock is a mixture of Slaters, Cooper Craft, London Road Models, Ratio and Bill Bedford. They all have sprung chassis from either Exactoscale, Bill Bedford or Brassmasters.

Most of the private owner coal wagons are POWSIDES kits.

We have painted, lined and weathered all of our own stock.

Running session

Operation of the layout is by a sequence of moves that involve two train operators and two fiddle yard operators.

The current sequence is made up of 43 moves.

Each train operator is given instructions including movement of locos/stock, signals required and any uncouplers required to complete the move. The train operator then selects the necessary track sections required and sets points accordingly.

Fiddle yard operator’s instructions include required arrivals/departures from each yard and the specific cassettes required to house the arriving loco/train.

The current sequence takes 2.5 to 3 hours to complete. One or two new trains are yet to be built and included which will take the sequence to around 40 moves.

Track plan

Trackplan courtesy of Gavin Clark – Scalefour Society